§ 1770-240. CESSATION OF WORK  


Latest version.
  • All work performed under a Grading and Erosion Control Permit shall be conducted in a manner so as to minimize the potential for discharge of sediment and/or pollution from the project site. Should any work performed under the permit be delayed for a period in excess of 15 calendar days, the permit recipient shall immediately notify the Director and shall take all steps necessary to prevent damage through erosion or sedimentation to:

    (a)

    Adjoining properties;

    (b)

    The public rights-of-way; and,

    (c)

    Any natural or artificial drainage facility or watercourse.

    If work is delayed for a period in excess of 90 calendar days, the Director may require the property subject to the permit to be graded so that it blends into the adjacent terrain.