§ 1060-310. CONSTRUCTION SCHEDULE  


Latest version.
  • (a)

    Within 90 days after acceptance of this franchise, the Grantee shall file all necessary applications to receive permits and authorizations which are required in the conduct of its business including, but not limited to, any utility joint-use attachment agreements, microwave carrier licenses and any other permits, licenses, and authorizations to be granted by duly-constituted regulatory agencies having jurisdiction over the operation of the cable television system, or associated microwave transmission facilities. In connection therewith, copies of all petitions, applications and communications submitted by the Grantee to the Federal Communications Commission, Securities and Exchange Commission or any other federal, state or regulatory commission or agency having jurisdiction with respect to any matters affecting Grantee's cable television operations shall also be submitted simultaneously to a Chief Administrative Officer.

    (b)

    Within two years after the commencement of construction pursuant to subsection (b) of this section, unless the Grantor in its discretion designates a shorter time in the franchise, Grantee shall complete construction and installation of the entire cable television system and proceed to render service to all residents of the Grantor who desire cable television service.

    (c)

    The Grantor may in its sole discretion levy a penalty not to exceed five hundred dollars ($500.00) per day for each day the Grantee exceeds the construction and installation timetable pursuant to subsections (a) and (b) of this section.